Depressurization System Safety Review: A HAZID-Based Approach — DSIB Case Study
Process plant at night with relief and flare-connected columns and piping
DSIB — Case Study
Relief & Depressurization  /  Safety Review

Depressurization System Safety Review: A HAZID-Based Approach

Drawn from an earlier revamp project on which DSIB principals held the risk and safety design role.
Client
A Large Chemicals Manufacturing Plant in Turkey
Scope
Engineering, Depressurization System Revamp & Safety Review
Context

A chemical production facility was revamping its relief, depressurization and flare system. Before the design moved into detailed engineering, a HAZID-based safety review was conducted to challenge the preliminary relief design basis, including fire-zone relief loads, flare routing, disposal philosophy and treatment system changes.

The study demonstrates front-end safety engineering in practice: making critical assumptions visible, clarifying unresolved design decisions and preventing safety-significant uncertainties from being carried silently into detailed engineering.

Approach

The review was structured as a HAZID-based safety review of the relief and depressurization design package. We didn’t run a generic checklist. We built the review around a Risk Breakdown Structure that mapped the full relief design lifecycle, then worked through it scenario by scenario over three facilitated sessions, anchored on a single fire zone as a worked case before propagating the same questions across the plant.

RISK BREAKDOWN STRUCTURE — RELIEF DESIGN LIFECYCLE 1 CONCEPTUAL DESIGN Rationale behind the revamp Normal and emergency venting scenarios Whether headers should be combined Treatment and intermediate treatment needs Preliminary header design and interactions 2 FINAL VENT HEADER DESIGN PHA revisions and MoC relevance Hazardous-area (HAC) revisions Earthquake, vibration and installation Disposal and treatment system assessment Maintainability 3 FLARE DESIGN Burner management and fuel Flame stability and compatibility Radiation, dispersion and toxic effects Cold vent alternatives Freezing, capacity, noise, air traffic and asphyxiation Emergency response assumptions As-built verification, installation constraints and vendor confirmation THREE FACILITATED SESSIONS · SCENARIO BY SCENARIO Anchored on a single fire zone as a worked case, then propagated across the plant
RISK BREAKDOWN STRUCTURE
01

Conceptual Design

  • Rationale behind the revamp
  • Normal and emergency venting scenarios
  • Whether headers should be combined
  • Treatment and intermediate treatment needs
  • Preliminary header design and interactions
02

Final Vent Header Design

  • PHA revisions and MoC relevance
  • Hazardous-area (HAC) revisions
  • Earthquake, vibration and installation
  • Disposal and treatment system assessment
  • Maintainability
03

Flare Design

  • Burner management and fuel
  • Flame stability and compatibility
  • Radiation, dispersion and toxic effects
  • Cold vent alternatives
  • Freezing, capacity, noise, air traffic and asphyxiation
  • Emergency response assumptions
  • As-built verification, installation constraints and vendor confirmation
Three facilitated sessions · scenario by scenario Anchored on a single fire zone as a worked case, then propagated across the plant.
Review architecture — schematic
Key Design
Decisions
Decisions taken04 See the details
01
Flare routing was selected as the main disposal route

The revised design did not foresee a new incinerator. Most PSV relief streams were routed to the flare system through a knock-out drum, while selected pressure-control discharges were retained through the existing incineration route.

02
Selected absorber credit was removed from the relief basis

For the reviewed process area, PSV reliefs were routed directly to the flare, and absorber credit was not assumed for the emergency relief composition. The flare composition basis was therefore required to reflect the revised routing without relying on absorber treatment during relief conditions.

03
Rupture disc plus PSV arrangement was supported for ammonia service

For ammonia-related relief systems, the review supported a rupture disc plus PSV arrangement as the provisional design solution, due to corrosion and leakage concerns affecting relief valve reliability. Vendor alternatives could still be considered if a more robust corrosion-resistant solution was proposed.

The review identified existing rupture disc plus PSV arrangements without a clearly documented basis. The decision was to move toward a consistent design philosophy by retaining rupture discs where justified and removing arrangements that did not meet the agreed philosophy.

04
A dedicated cold vent was foreseen for 100% ammonia relief

For ammonia storage and anhydrous ammonia relief, the final disposal route was not treated as a simple routing decision. Flare routing, cold venting and direct venting options were considered, with the final decision linked to atmospheric dispersion modelling and consequence evaluation.

For 100% ammonia relief, a new dedicated cold vent was foreseen in the design. The associated dispersion modelling was identified as a required basis for confirming the suitability of this release path.

Design basis established03 See the details
05
Fire-zone relief loads were based on conservative fire assumptions

The relief load basis treated the relevant fire zones conservatively, including cases where fireproofing was not credited. Where elevated equipment or local fire exposure assumptions could affect relief loads, the design required further confirmation against actual site conditions.

06
Gas breakthrough cases were added to the basic design basis

Gas breakthrough scenarios were reviewed to confirm whether high-pressure gas could unintentionally pass into downstream low-pressure systems and create additional overpressure or relief load case. The engineering team was expected to identify relevant gas breakthrough cases and include them in the corresponding PSV datasheets during basic design package preparation.

07
Tube rupture scenarios were evaluated

Tube rupture scenarios were reviewed as part of the relief design basis. The engineering team confirmed that these scenarios had been evaluated. However, the owner was expected to identify any additional field configuration or reactor protection arrangement that may not have been reflected in the design.

Held open for confirmation04 See the details
08
The flare header network was defined as a design gate

The flare header network had to be finalized before the relief design could be considered mature. The review confirmed that the flare header network document was completed, but also identified that detailed engineering calculations should be checked against verified field configuration because routing documentation may not fully represent the existing installation.

09
PSV type selection was linked to final backpressure

The review established that PSV type selection could not be finalized until flare header backpressure was confirmed. The engineering team was expected to define the required PSV types after backpressure confirmation, and the owner would compare these requirements against the existing installed equipment.

10
Vendor confirmation was required for chattering and valve performance

Potential PSV chattering was not accepted as a generic assumption. A list of potentially affected valves was to be developed and reviewed with instrument discipline and relevant vendors before the selected valve arrangements could be accepted.

11
PCV-based pressure balancing for ammonia storage required HAZOP review

For ammonia storage pressure management, the use of pressure-control-based balancing rather than relying only on relief valves was considered. The decision was that this concept would require renewed HAZOP review before being accepted as part of the operating or protection philosophy.

Highlights
52
Total number of findings for a single fire zone
34/52
Ratio of safety-critical findings / immediate action addressed
31
Findings concentrated in two technical areas: vent header / PSV preliminary design and emergency venting scenario basis
Recommendations
01

Verify As-Built Configuration Before Design Closure

See the details

Relief and flare calculations should be checked against approved as-built P&IDs, isometrics and actual field configuration. Routing, slope-liquid accumulation, free-draining requirements, isolation arrangements and installation deviations should be verified before closing the design.

02

Align Relief Design with HAZOP and Credible Scenarios

See the details

The PSV list, overpressure scenarios and relief loads should be reconciled with existing HAZOP and PHA records. Power failure, ESD, blocked outlet, gas breakthrough, tube rupture, fire exposure and abnormal operating cases should be systematically checked.

03

Manage Disposal Changes as Safety-Critical Decisions

See the details

Changes such as absorber removal, incinerator elimination, flare routing or cold venting should be managed as safety-critical design decisions. They should be supported by MOC, dispersion modelling, toxic consequence assessment and emergency response review.

04

Establish a Consistent Rupture Disc Philosophy

See the details

Rupture disc and PSV combinations should follow a consistent design philosophy across the system. The project should define where rupture discs are required, where they should be removed, and how corrosion, leakage and maintenance issues will be managed.

05

Confirm PSV Performance with Evidence

See the details

PSV type, set pressure, backpressure tolerance, chattering risk and material compatibility should be confirmed with sufficient engineering evidence. Vendor input should be obtained where valve performance depends on service-specific or equipment-specific data.

06

Confirm Purge Gas, Fuel Support and Flare Stability

See the details

Purge gas supply, methane support, positive pressure maintenance and flame stability should be confirmed before accepting the flare basis. The flare should be assessed for both normal operation and abnormal relief conditions.

07

Improve Relief Event Awareness

See the details

The design should consider how operators will know when relief occurs, especially in remote or less visible areas. Additional indication, such as temperature monitoring at unit flare header outlets, may improve operational awareness and response.

08

Link Flare Design with Emergency Response

See the details

Flare design should be connected to emergency response planning, especially where toxic or ammonia-containing streams are routed to flare. Emergency teams should understand lit and unlit flare scenarios, flame-out conditions and potential toxic release consequences.

Design Safety Intelligence Bureau
Case Study Reporting Series

© Design Safety Intelligence Bureau. All rights reserved. This document and its contents may not be copied, reproduced, distributed, downloaded or printed, in whole or in part, without prior written permission.

Design Safety Intelligence Bureau — Case Study Reporting Series. This document may not be printed or reproduced without prior written permission.